Atten:Subang Co-generating Power Plant Put into Operation

Hittimes:1466 Addtime:2008-09-14

After examine start-up, shut down, co-operation and output of Boiler No.1 and No.2, Subang Co-generating Power Plant, contracted by SCMEC in Indonesia had successfully passed 72-hour commissioning at local time 00:56am on September 14, 2008 and handed over to the Owner.

This is another important milestone for our corporation after handed over Waylunik Co-generating Power Plant to the Owner on April 8, this year.